The
Prairie du Sac school board approved Verizon’s cell tower proposal in March to
construct an 80-foot light pole near the high school’s athletic field where
cellular phone companies would add communications antennas, making the height
of the tower 150 feet.
The
school board approved the lease agreement with a 5-2 vote, even though many
members of the community were against this proposal. The cell tower includes an
annual payment of $15,000 per year to the school district. Even though the
school district approved the lease, Verizon must still obtain the correct
building permits.
While
many of the residents of the community are upset over this project, there isn’t
a lot they can do to stop the construction from happening. On July 1st,
Wisconsin adopted a new state law that restricts the ability of local
governments to regulate the placement of cellular towers.
Kim
Lamoreaux of The Eagle reported that,
“Under the new state law, municipalities are
required to rule on a wireless tower permit application within 90 days or the
application will be automatically considered approved. Local officials can deny
a permit if the applicant refuses to consider putting equipment on a tower
shared with other wireless providers, but there are few other reasons available
to local governments for a denial.”